Spa and Kids' Pool Upgrade Announcement
|
We are pleased to announce that the Bali Dynasty Resort will be making some minor improvements to its' facilities from the 1st of February 2012 with an upgrade of the kids pool and the construction of a new spa. Both areas are located to the south westerly and north westerly points of the property and therefore disruption is expected to be minimal. In order to further enhance our Resort facilities for Kids as well as being considered one of Bali's Best Family Resorts we will be adding a "Kids Water Fun Zone" and refurbishing the kids pool. We will also be building a new spa facility which will provide 10 air conditioned rooms and 16 massage beds.
|
Project Work Area
|
KIDS POOL
|
|
STAGE 1 |
|
Start Date :
Completion Date :
|
1st February 2012
29th February 2012
-
The kids pool and waterslide will be closed for this duration.
-
The Kids Club and Kids Play area will operate as normal
-
The Baby Paddling Pool next to the Sunken Bar will be temporarily available during the month of February.
|
|
Scope of Work |
-
Refurbishment of existing waterslide, retiling and enlarging of existing Kids pool area (north side)
|
|
Inconvenience |
-
The Waterslide will re-open on the 1st March 2012.
-
The Kids Pool and water slide will be closed until 29 February 2012
|
|
Level of disturbance |
-
Little noise disturbance at the Kids Club
-
No rooms directly facing over the kids pool
-
The whole area will be completely screened off to minimize disturbance
|
|
|
|
STAGE 2 |
|
Start Date :
Completion Date :
|
1st March 2012
4th April 2012
-
The southern side of the kids pool (next to kids club) will remain closed in order to complete the Kids Water Fun Zone
-
The Kids Club and Kids Play area will operate as normal
|
|
Scope of Work |
-
Adding the Kids Water Fun Zone which will include water playground equipment such as mini water slide, pull ropes, water curtain, tipping cone, bubbler jets, hose jets and tipping trough
|
|
Inconvenience |
-
No baby paddling pool available during this period
|
|
Level of disturbance |
-
The whole area will be completely screened off to minimize disturbance
-
No rooms directly facing over the kids pool
|
|
Hours of Work |
-
9am - 6pm, 7 days a week
-
All other facilities will be available as normal
|
|
Project Work Area |
SPA VILLA |
Start Date :
Completion Date : |
1 February 2012
31 May 2012 |
|
Scope of Work |
-
Complete removal of the existing Spa Villa and Massage Bale in order to make way for a new two storey Spa
|
|
Inconvenience |
-
Limited Spa Menu available
-
Spa facilities will be moved temporarily to the upper deck of the Sunset Deck and to a ground floor pool facing room
-
Lazy pool (Adult Zone) will be limited
|
|
Level of disturbance |
-
Access to the work area will be fully screened off to minimise noise and dust disturbance
-
No rooms directly facing over the Spa Project
-
Lazy pool could experience some noise disturbance in the initial few weeks
-
North Wing outer garden rooms will have a screen in front to divide the project access and give privacy to our guests (mainly Kids Suites)
|
|
Hours of Work |
-
9am - 6pm, 7 days a week
-
All other facilities will be available as normal
|

|